Client: Taylor Wimpey

Area: Phase 10, Peugeot Works Coventry

Requirement: Cantilever scaffold for access

Access was required between two plots at Coventry to enable the fork lifts entry to a courtyard area. However plots 471 -474 still needed to be constructed to ensure the site stayed on programme. In conjunction with Reactive Design, Airwright Midland erected cantilever scaffolds to the gable ends of both properties which were connected together at a height of 4m to enable the access required.