Access scaffold platform to SS5 Partition wall
Client: Vinci Construction for a leading car manufacturer i54 Wolverhampton
Area: MH1
Requirement: Access scaffold platform to SS5 Partition wall
A free-standing scaffold structure was required by VCUK to enable the completion of a Middas partition wall. Due to the nature of the wall finish, the scaffold could not be tied into the structure so a buttress scaffold was required to stabilise the scaffold.
Airwright Midland design partner Reactive Design produced a bespoke design for a scaffold that was 30m in length and 14m high with a 2KN/m² live load allowance @ 1 no lift
Related Projects

Loading bay at i54 Wolverhampton
A 5m x 6m on plan loading platform was required to be built on the spine roof to service the main roof area for JLR i54 Wolverhampton. Read more >>

Screen wall to SS5/MH1 for a leading car manufacturer
A scaffold screen wall was required to ensure a building end encapsulation for concreting works to be completed at floor level. Read more >>

Material Planning and Logistics canopy roof
A scaffold laydown was required to be built off existing steelwork to enable works at high level to ducting and cable trays. Read more >>

Our housing development projects
We specialise in residential scaffolding solutions for a number of national housebuilders, and can deliver a high volume of supporting structures at any one time.... Read More >>

Queen Elizabeth Hospital
Airwright Midland provided internal and external access scaffolds to VCUK to enable the complete refurbishment.... Read More >>

Jaguar Land Rover, Lode Lane, Solihull
Airwright Midland provided VCUK full perimeter edge protection to new building, roof areas, lift shafts and stair cores.... Read More >>